| Current status of project:
Initial design ideas have been discussed and recorded. The specifications, advantages, and disadvantages have been listed for each idea. The web page structure is being discussed, and the specifications are being tracked down. Work completed in the Last week:
What the group is currently working on:
What the group is planning next:
|
WEEK 2: 1-28-02
| Current Status of the Project:
We have started working on the preliminary presentation. Ideas have been organized and put on paper. We have also done a fair amount of research and collected quite a bit of information via literature and patent searches. The web-page skeleton in up and can be viewed at students.cec.wustl.edu/~kp8 Work Completed in the Last Week:
What the group is currently working on:
What the group is planning next:
|
WEEK 3: 02-04-02
| Current status of project :
This week, we have been getting ready for the presentation and finishing up the written report. We discussed some aspects of the written report with Dr. Silva and asked his opinion on a few issues. Work Completed in the Last Week:
What the group is currently working on:
What the group is planning next:
|
WEEK 4: 02-11-02
| Current status of project :
At this point, we have finished presentation material as well as are putting finishing touches to the written report. We have finished a pugh chart and have decided in favor of the electromagnetic actuator. Work completed in the Last Week: The presentation went well. The written report has almost been completed and ready to be turned in. What the group is working on: Since the actuator and the spring motor system both scored high in our pugh chart analysis, we are working on trying to decide between the two systems for our final design. What the group is planning next: After have chosen a particular design, we shall try to come up with an initial layout of the design and decide on various aspects of the design and components that we might need for our system. |
WEEK 5: 02-18-02
| Current Status of the Project:
We have decided on the specific design of the project- the speaker driven by the electromagnetic coil. Our mentor has also noted that he believes that this alternative seems the most plausible. We have allocated responsibilities to each of the members for the upcoming problems and design parameters. The updated web-page is almost completely up and can be viewed at students.cec.wustl.edu/~kp8 Work Completed in the Last Week:
What the group is currently working on:
What the group is planning next:
|
WEEK 6: 02-25-02
| Current Status of the Project:
We have decided on the specific design of the project- the speaker driven by the electromagnetic actuator. Our mentor has also noted that he believes that this alternative seems the most plausible. We have allocated responsibilities to each of the members for the upcoming design parameters and presentation. The updated web-page can be viewed at students.cec.wustl.edu/~kp8 Work Completed in the Last Week:
What the group is currently working on:
What the group is planning next:
|
WEEK 7: 03-04-02
| SPRING BREAK |
WEEK 8: 03-11-02
| Current status of project :
Each group member is researching and gathering information in his area. Also, we have been getting ready for the presentation and starting on an outline for the written report. What the group is working on now: The group is involved in finishing up the slides etc. for presentation while also working on the final draft of the progress report. What group is planning next: Control system would be a major emphasis during the next few weeks. |
WEEK 9: 03-18-02
| Current Status of the Project:
We have finished the second presentation and written report. We have determined the design and most of the components needed. The updated web-page can be viewed at students.cec.wustl.edu/~kp8 Work Completed in the Last Week:
What the group is currently working on:
What the group is planning next:
|
WEEK 10: 03-25-02
| Current status of project :
Michael Dahl met with Dr. William Murphy and discussed the open versus closed loop control system. In the end it was decided that an open loop control system would be most suitable for our project at hand. We also received correspondances from the vendors, namely CSA engineering, Kistler, etc. What the group is working on now: The group is working on integrating the components together and acconting for the mismatches between the input and output sources of various components by using amplifiers. So far we have determined that the amplifier set for the transducer is available at kistler itself and we still have to find out about the amplifier between the wave generator and the actuator. What group is planning next: We are going to talk to Michael Evert from CSA engineering and get more clarifications on the amplifier that can be used to correct the mismatch between the function generator output and the input into the amplifier. |
WEEK 11: 04-01-02
| Current status of project :
At this time, we have all the information about the various components, the biomechanical analysis is almost complete and the calculations of various component parts are in progress. In other words we have all the required information in order to make a final draft of our design proposal. What the group is working on now: We are gathering all the information and putting it together. We are also preparing for the presentation and the final written report. What group is planning next: Wrap up the project and get ready for the presentation. |